Skip to main content
Ir a la página de inicio de la Comisión Europea (se abrirá en una nueva ventana)
español es
CORDIS - Resultados de investigaciones de la UE
CORDIS

NEW DIAPHRAGM WALL JOINT SYSTEM ALLOWING GREATER DEPTHS AND HIGH QUALITY JOINTS

Periodic Reporting for period 7 - TTMJ (NEW DIAPHRAGM WALL JOINT SYSTEM ALLOWING GREATER DEPTHS AND HIGH QUALITY JOINTS)

Período documentado: 2019-09-01 hasta 2020-02-29

Guide tracks fixed on the pre-cast beams during tests
The slanted concrete beam after trimming
The concrete block after sawing. Visible the joint and the GFRP pipes
The trimmer suspended by the base carrier, ready to start the tests
Simplified sketch of the tension joint arrangement
Split tests runned by Politecnico of Milan on three sawed samples
The TTMJ trimmer machine
Principal roles of TTMJ project consortium members